News at the end of projects of the administration

Results of the 20th VP-V portfolio board meeting (25/09/2025)

At the 20th meeting of the VP-V-PPB, two projects were completed (introduction of 2-factor authentication for user accounts, preliminary project conversion SAP R/3 to SAP S/4 HANA) and one project proposal was approved (system conversion SAP S/4 HANA).

At the 20th VP-V project portfolio board meeting...

...the project "Introduction of 2-factor authentication for user accounts" was completed. The project aimed to improve security in the university network by using a second factor. The project ran from 03/2024 - 04/2025.

...completed the preliminary project "Conversion SAP R/3 to SAP S/4 HANA". The aim of the project was to determine the necessary preparations for the upcoming SAP migration and to support the main project. The project ran from 04/2024 - 06/2025.

...the major project "System Conversion SAP S/4 HANA" was released. The SAP migration to S/4 HANA is being carried out as part of the project. The project is planned to run until 2028.